August 1 - September 11, 2024
Many levels of planning, engineering, testing, and earthwork that have led up to an essential part of the project! We have started laying sod and seeding on holes 2,3,4,9,10,18. Exciting time to be a part of a very special project as Mapletøn Golf Club comes to life! This important part of the proje...
June 21st – August 1st , 2024
Since the rains subsided in late June, the project was met with ideal dry conditions over the last 40 days.This has allowed for significant progress to occur throughout the entire site – both golf course and up atthe north end with the buildings. Here is a recap of the accomplishments:Golf Course Co...
May 8th – June 20th , 2024
On May 21st , Landscapes Golf Course Construction H2B team of 45 skilled golf course laborers showedup for the season to join the dozen or so already on site. A crew of 59 from Landscapes plus workersfrom Soukup Construction have been making significant progress throughout the past month despite the...
April 8th - May 7th, 2024
The month of April was a little more challenging to the golf course construction crew. While we have still been very blessed with the amount of progress made year to date, we did encounter 8 lost workdays and over 9" of moisture in the past month. Here is a recap of what we have accomplished during ...
March 25th – April 7th, 2024
The last week of March brought our first "weather days" of the spring 2024 season. The Sioux Falls area received some much-needed moisture around the Easter Holiday Weekend and a couple days off were needed to dry out the site. During this two week period, the focus of work included: Mass Earthwork/...
March 2024 Update
Just 60 days after turning the dozers off for winter, the crew from Soukup Construction was back at it on February 26th. Yes you read that right. February 26th. In South Dakota. The frost is out of the ground and the temperatures have been consistently mild. The team has been able to work unimpeded ...
December 2023 Update
On October 30th, 2023 the first dozer was unloaded at sunrise and work commenced at the 10th green. The beginning of construction was the culmination of fifteen months of intense planning and coordination along with the genuine excitement and support of the local community. The same afternoon, despi...